This page is maintained for older versions of Spira only. The latest documentation can be found at: https://spiradoc.inflectra.com

Spira 4.2 User Manual Help Viewer

1. Introduction
2. Functionality Overview
3. User/Project Management
4. Requirements Management
5. Test Case Management
6. Incident Tracking
7. Release Management
8. Task Tracking
9. Resource Tracking
10. Document Management
11. Reports Center
12. Source Code
13. Planning Board
14. Mobile Access
Search:
1. Introduction
2. Functionality Overview
3. User/Project Management
4. Requirements Management
5. Test Case Management
6. Incident Tracking
7. Release Management
8. Task Tracking
9. Resource Tracking
10. Document Management
11. Reports Center
12. Source Code
13. Planning Board
14. Mobile Access

13.4.3. Iteration Backlog – Tasks by Person

This view is designed to let you see the tasks in the current iteration / sprint plan organized by resource / person. Each of the users that is a member of the current iteration is displayed as a heading, with the tasks displayed in the same column underneath. This view is often called the Task Board:

You can click on the expand/collapse icons to hide any resources that are not relevant. The system will display a progress bar for each resource to illustrate the allocation for that resource. Any resource that has a progress bar that is completely green has been fully scheduled and should not have any additional tasks assigned. If the progress bar for that resource turns red, it means that they have been over-scheduled and you need to reassign some of the tasks.

Above the resource headings there are sections with the release and iteration name; they contain tasks that are scheduled for the current release or iteration but have not yet been assigned to a resource. You can drag and drop the tasks between resources or to/from the release/iteration backlog. Any tasks not assigned to a resource and release/iteration will be listed in the (Unassigned Items) section at the top.