Hi, I'm evaluating SpiraTest / SpiraTeam but there is one thing I can't figure out.&#xD;
&#xD;
    How to handle test cases for a requirement?      Example: I have created a test case linked to a requirement, the test case is executed then the requirement changes. There seems to be no way to trigger an event for this change? How do I know which tests to re-test? Can I find the associated tests for a changed requirement by filter/search somehow? If not, is there any other recommended way to handle requirement change? I can't seem to find a way to handle requirement versions, e.g. v1 of the test case is executed towards v2 of the requirement? What is best practice in SpiraTest for this?       </description><language>en-US</language><copyright>(C) Copyright 2006-2026 Inflectra Corporation.</copyright><managingEditor>support@inflectra.com</managingEditor><category domain="http://www.dmoz.org">/Computers/Software/Project_Management/</category><category domain="http://www.dmoz.org">/Computers/Software/Quality_Assurance/</category><generator>KronoDesk</generator><a10:contributor><a10:email>support@inflectra.com</a10:email></a10:contributor><a10:id>http://www.inflectra.com/kronodesk/forums/threads</a10:id><ttl>120</ttl><link>/Support/Forum/spiratest/issues-questions/1340.aspx</link><item><guid isPermaLink="false">threadId=1340</guid><author>Mikael Rosquist (mikael.rosquist@cybercom.com)</author><category domain="http://www.inflectra.com/kronodesk/thread/tag">test sets</category><category domain="http://www.inflectra.com/kronodesk/thread/tag"> suspect</category><title>How to handle tests for changed requirements, or requirement change process overall</title><description>&#xD;
Hi, I'm evaluating SpiraTest / SpiraTeam but there is one thing I can't figure out.&#xD;
&#xD;
    How to handle test cases for a requirement?      Example: I have created a test case linked to a requirement, the test case is executed then the requirement changes. There seems to be no way to trigger an event for this change? How do I know which tests to re-test? Can I find the associated tests for a changed requirement by filter/search somehow? If not, is there any other recommended way to handle requirement change? I can't seem to find a way to handle requirement versions, e.g. v1 of the test case is executed towards v2 of the requirement? What is best practice in SpiraTest for this?       </description><pubDate>Fri, 18 Dec 2015 12:26:00 -0500</pubDate><a10:updated>2015-12-23T16:46:07-05:00</a10:updated><link>/Support/Forum/spiratest/issues-questions/1340.aspx</link></item><item><guid isPermaLink="false">messageId=2434</guid><author>Inflectra Sarah (donotreply6@kronodesk.net)</author><title>&#xD;
Hi Mikael&#xD;
&#xD;
    There is no event currently triggered (planned enhancement) however you can run a</title><description>&#xD;
Hi Mikael&#xD;
&#xD;
    There is no event currently triggered (planned enhancement) however you can run a Requirements Traceability Report and then see which of the test cases needed to be executed based on requirements that changed in a specific date range?   Regards     Sarah </description><pubDate>Wed, 23 Dec 2015 16:46:07 -0500</pubDate><a10:updated>2015-12-23T16:46:07-05:00</a10:updated><link>/Support/Forum/spiratest/issues-questions/1340.aspx#reply2434</link></item></channel></rss>