Incident link issue from SpirTeam to JIRA

Monday, September 8, 2014
Avatar
Hi,

I am working on an integration Spira Team incident with Jira issue. I am using Desktop sync plugin for this issue linking between Jira and SpiraTeam. I have done all the settings according to the inflectra documentation. Worked on Plugin mapping, Project mapping, standard field mapping and done with custom filed mapping.

New Issues in Jira are linking from JIra to Spira and I can see the issue link in JIta. However, I am not getting why the issue in SpiraTeam is not linked in other way i.e. from Spira to JIRA. 
 
Thanks
Swachand  
1 Replies
Thursday, September 11, 2014
Avatar
inflectra.jimx
re: jambhus Monday, September 8, 2014
Hi Swachand

It should work that way as well. Most likely there is an error in the synchronization.

Please go to Administration > System > Event Log and see if there are any synchronization errors.

If so, please email them to support@inflectra.com or log a help desk ticket with the information.

Regards
Jim

Spira Helps You Deliver Quality Software, Faster and With Lower Risk

And if you have any questions, please email or call us at +1 (202) 558-6885

 

Statistics
  • Started: Monday, September 8, 2014
  • Last Reply: Thursday, September 11, 2014
  • Replies: 1
  • Views: 2019