For a given release and sprint how can planned dates be added to the "Test Case Cumulative Progress" Widget?
Business Scenario
1. Release - 1
Sprint1-UAT1
Total Test cases - 300
Challenge - Since there are about 300 test cases. It will be difficult to input the planned number against each of those 300 test cases.
How can this project in the "Test Case Cumulative Progress" widget? Or, is there a way to build a custom report or Planning Options?
We are trying to minimize the use of Excel here. Please advise.
Typically we'd recommend using the Planned Date for the Test Set and group the test cases in the release/sprint into batches by test set. You could otherwise add a Planned Date custom property to the test case.
For reporting questions, you could then use a custom query to select the test cases by this new planned date field or by sprint, etc.