Best approach for accurately reflecting bandwidth on the Planning Board

Wednesday, August 14, 2013
Avatar
What is the best approach to have the Planning Board accurately reflecting the available bandwidth? For instance we have individuals that maybe are only available for 50% of a Sprint or may not partake at all in a Sprint yet the Planning Board and everywhere else it projects available bandwidth assumes everyone is available? I would like to say Person 1, Person 2, are out for this Sprint and thus are not visible on the Planning Board.
1 Replies
Monday, August 19, 2013
Avatar
re: aaron_mciver Wednesday, August 14, 2013

Hi Aaron

To handle partially allocated resources, you would need to adjust the non-working days in the Release / Iteration to reduce the amount of available time to account for the partial resources. In the future we plan on adding support for partial allocations.

Regards

Adam

Spira Helps You Deliver Quality Software, Faster and With Lower Risk

And if you have any questions, please email or call us at +1 (202) 558-6885

 

Statistics
  • Started: Wednesday, August 14, 2013
  • Last Reply: Monday, August 19, 2013
  • Replies: 1
  • Views: 5879