Best approach for accurately reflecting bandwidth on the Planning Board

Wednesday, August 14, 2013 4:39:41 PM
What is the best approach to have the Planning Board accurately reflecting the available bandwidth? For instance we have individuals that maybe are only available for 50% of a Sprint or may not partake at all in a Sprint yet the Planning Board and everywhere else it projects available bandwidth assumes everyone is available? I would like to say Person 1, Person 2, are out for this Sprint and thus are not visible on the Planning Board.
1 Replies
Monday, August 19, 2013 1:19:18 PM
Avatar
re: aaron_mciver on Wednesday, August 14, 2013 4:39:41 PM

Hi Aaron

To handle partially allocated resources, you would need to adjust the non-working days in the Release / Iteration to reduce the amount of available time to account for the partial resources. In the future we plan on adding support for partial allocations.

Regards

Adam