Task management across Projects/Groups RSS Feed

Friday, August 5, 2011
Seeing that reporting and querying in SpiraTeam seemingly works on a Project-level only, how do you recommend that a Team Manager view and track the o/s Tasks across a multi-Project team?

Each individual User can see their current Task queue in their My Page feature, but how can a supervisor see multiple Tasks/Resources in one view/report?

1 Replies
Adam SAdam S
re: Andy Smith on Friday, August 5, 2011
Friday, August 26, 2011

We plan on adding this feature, but for now you'd need to create custom reports of your own by querying the TST_TASK table of the database directly.