Hi,
Our program consists of 8 projects (or software configuration items in IEC62304 speak).
At the moment we are on 6.5.0.0 which doesn't have baselining but we're thinking of moving to the latest edition of SpiraPlan.
Question - is it possible to have a program-wide baseline? What I mean is that once baselined, all artefacts (requirements, tests, sprints, etc) are baselined, allowing us to take a snapshot of the entire program?
Hello,
The baselines themselves are created inside each product (not at the program level), but ultimately the history changeset ID, which is the fundamental record of the changes in the system, are system-wide, so the values are comparable across the entire system (and therefore across an entire program).
Regards
David