Release Summary Report Seems Inaccurate RSS Feed

Wednesday, May 22, 2013
I ran a release summary report and under our week one iteration it says that there are 0% of the tasks not started.  However I go into a requirement that is associated to that iteration and there are many tasks that say not started.
1 Replies
Adam SAdam S
re: S Wycoff on Wednesday, May 22, 2013
Thursday, May 23, 2013

In general if the tasks don't have any effort value (i.e. are zero hours) they will not get counted towards the requirement or release/iteration totals since we weight the values by effort.

If that doesn't explain the issue, could you submit a help desk ticket with some screenshots, that way we can better assist you?

Regards

Adam