Make Actual Time / Estimated Time in Tasks Mandatory? RSS Feed

Friday, February 14, 2014

This might be a dumb question, but how do I make the "Actual" and "Estimated Time" fields for Tasks mandatory?
1 Replies
Sarah T.Sarah T.
re: Erin M Egleston on Friday, February 14, 2014
Monday, February 17, 2014
Hi Erin

We added workflow capability for tasks (and requirements) in v4.1, so please make sure you're running v4.1 and then you can:
- Go to Administration > Planning > Task Workflows
- Click on the 'Steps' link for the current Task Workflow
- Click on the status that you want the effort to be mandatory for.
- On the page that appears, set the 'Required' flag for the appropriate effort fields
- Click Update/Save