Make Actual Time / Estimated Time in Tasks Mandatory?

Friday, February 14, 2014 6:58:21 PM
Hi,

This might be a dumb question, but how do I make the "Actual" and "Estimated Time" fields for Tasks mandatory?
1 Replies
Tuesday, February 18, 2014 2:42:42 AM
Avatar
re: eegleston on Friday, February 14, 2014 6:58:21 PM
Hi Erin

We added workflow capability for tasks (and requirements) in v4.1, so please make sure you're running v4.1 and then you can:
- Go to Administration > Planning > Task Workflows
- Click on the 'Steps' link for the current Task Workflow
- Click on the status that you want the effort to be mandatory for.
- On the page that appears, set the 'Required' flag for the appropriate effort fields
- Click Update/Save

Regards

Sarah