Hi, New to SpiraTest and was wondering how you set up seperate testing phases. How do you ensure that the next phase doesn't start until the previous phase is complete?
1 Replies
Wednesday, February 13, 2013
Avatar
re: harrowj Monday, February 11, 2013

Hi Jon

Generally you would use the Releases and Iterations (under the Planning > Iterations section) to handle this.

You create Releases for the major versions and then Iterations for the different phases (waterfall project) or sprints (agile project).