We are evaluating the use of RemoteLaunch to automate tests and have a product we are testing using Testcomplet 10 and Spiratest.

We have the automation working just fine.

We are unable to control the execution order in which RemoteLaunch executes test sets.

We have a test set that is dependent on the previous test set completing successfully. How can we establish that relationship within SpiraTest?

Can we control the test set execution order? We read it should honour the TestSet ID order but that didnt work, the test set with the higher order number ran first.

Any assistance would be greatly aprpeciated.

 

1 Replies
Wednesday, November 19, 2014
Avatar
re: gcause Tuesday, November 18, 2014

(Grant asked this question in the Help Desk as well. I'm copying Adam's answer here.)

Hi Grant,

Unfortunately test sets are designed to be independent of each other. If you need the tests to be executed in a specific order, they need to be part of the same test set in the specific order. We are looking to add this type of functionality in the future.

Regards,

Adam

Spira Helps You Deliver Quality Software, Faster and With Lower Risk

And if you have any questions, please email or call us at +1 (202) 558-6885

 

Statistics
  • Started: Tuesday, November 18, 2014
  • Last Reply: Friday, October 14, 2022
  • Replies: 1
  • Views: 2788