I use SpiraTest to control integration test scenarios. These scenarios could take even few days to complete as several parties are involved. However such test cases/test sets are still in "not run" status. I can't see how many such cases/sets are "in progress" except in "My Page".

Would be nice to add status "in progress" and show this in "Project Home" review.

3 Replies
Adam SAdam S
re: Hynek Klicka on Wednesday, July 20, 2011
Tuesday, July 26, 2011
On the Testing > Test Sets page you should be able to see the progress of the various test sets that you have assigned to people. The colored bar indicates what % have been executed...
Hynek KlickaHynek Klicka
re: Adam S on Tuesday, July 26, 2011
Tuesday, July 26, 2011
This is only partially true. Progress bad "move" is trigered only by finished test cases. A test case with 5 steps which is paused at step 3 is still shown as "not run".
Adam SAdam S
re: Hynek Klicka on Tuesday, July 26, 2011
Tuesday, August 2, 2011
Yes we only report the status when a test case has been either completed passed or has at least one step failed/blocked/caution.
  • Started: 7/20/2011
  • Last Reply: 8/2/2011
  • Replies: 3
  • Views: 661