Test Result on Linked Scenarios

Friday, April 5, 2013 9:33:57 AM
Hello,

We have created Test Scenarios in SpiraTest (v4.0) using parameters, and we linked them with other scenarios, changing only the values of the parameters.
However, when we record the result of a linked scenario, it immediately alters the result of the parent scenario.
This results the display of the parent scenarios as executed, with no test run information which seems a bit confusing.

Is it possible for the parent scenarios to remain "Not Run" until they are actually executed?

Thank you in advance.
2 Replies
Monday, April 8, 2013 11:01:28 AM
Avatar
re: Fotini on Friday, April 5, 2013 9:33:57 AM

Hi Fotini

I have checked with our development group and unfortunately there is no option to change how this works.

Regards

Adam

Monday, April 8, 2013 12:15:11 PM
Avatar
re: inflectra.adam on Monday, April 8, 2013
Thank you for the enquiry and reply! :)

Statistics
  • Started: Friday, April 5, 2013 9:33:57 AM
  • Last Reply: Monday, April 8, 2013 12:15:11 PM
  • Replies: 2
  • Views: 881