Remote launch executes test set at the same time

Tuesday, February 20, 2018
Avatar

Hi,

I am sending multiple test sets to remote launcher from SpiraTest. Remote launcher usually executes test sets one by one but some times it executes 2 test sets at the same time and I don't want that. Why remote launcher execute multiple test sets at the same time? I can't solve this problem.

Thank you.

2 Replies
Tuesday, February 20, 2018
Avatar
inflectra.jimx
re: AnilEkmekci Tuesday, February 20, 2018

Hi Anil,

We have released an updated RemoteLaunch (v5.0) that fixes this issue.

Regards

Jim

Wednesday, February 21, 2018
Avatar
re: inflectra.jimx Tuesday, February 20, 2018

Hi Jim,

I updated to latest release(v5.0.0.0). Issue is not resolved completely. I am sending 26 test sets at the same time, in old version (v4.0.8) RemoteLaunch starts to execute multiple test set at the very beginning, in updated version (v5.0.0.0) RemoteLaunch starts to execute multiple test set at the last couple test sets. There was a progress but same problem continues.

Do you have any recommendations for me?

Spira Helps You Deliver Quality Software, Faster and With Lower Risk

And if you have any questions, please email or call us at +1 (202) 558-6885

 

Statistics
  • Started: Tuesday, February 20, 2018
  • Last Reply: Wednesday, February 23, 2022
  • Replies: 2
  • Views: 5815