How to use effort fields

Wednesday, March 23, 2011
Avatar
 How does one use the "effort" fields (e.g., the Planned Effort field in the Requirement Details screen and the other Effort fields in the Task Details screen).
2 Replies
Wednesday, March 23, 2011
Avatar
re: inflectra.david Wednesday, March 23, 2011
The effort fields are used as follows:
- Requirement Planned Effort = the high level 'top-down' initial estimate of the functionality at the "user story" level
- Task Estimated Effort = the developer estimate of how long each task will take. The system will sum these up to the parent requirement so that this 'bottom-up' estimate can be compared with the original top-down estimate
- Task Remaining Effort = the amount of time during development left to complete the task (updated by the developer during development) - indicates the % complete
- Task Actual Effort = the amount of time taken by the develop (so far) in completing the task.

The Projected Effort is a read-only field that gives an indication of the final total estimate for the task based on the actual hours consumed and the time remaining.

Thursday, February 20, 2014
Avatar
re: inflectra.david Wednesday, March 23, 2011
I have the same question actually. How can I register "Actual Effort" on daily basis, and then get for example a month or quarter report on "Acutal effort" per day, per week, etc.?
Statistics
  • Started: Wednesday, March 23, 2011
  • Last Reply: Thursday, February 20, 2014
  • Replies: 2
  • Views: 13075