synchronization between test case and incident

Wednesday, October 17, 2012 9:55:33 AM
Hi,

I have a question about synchronization between the incidents and test cases.
I want that when i close an incident associated with a step, the step changes to PASS status. There are a setting available to make this?
Or in other way:  if a test case which has an associated incident, is changed to PASS status, is possible to close the related incidents automatically?
1 Replies
Wednesday, October 17, 2012 5:17:46 PM
Avatar
re: xmauricio on Wednesday, October 17, 2012 9:55:33 AM

Hi Mauricio

There is not currently a setting to make this change happen automatically. The reasoning (at the time) was that it was important to have the test independently executed before setting it to pass. We are considering adding a setting to allow this in the future.

Regards

Adam

Statistics
  • Started: Wednesday, October 17, 2012 9:55:33 AM
  • Last Reply: Wednesday, October 17, 2012 5:17:46 PM
  • Replies: 1
  • Views: 635