Skip Navigation LinksHome Page > Forums > SpiraTeam Forums > SpiraTeam Issues & Qu... > Resource Load Balance in ...
Hi Ben
In answer to your specific questions:
1) You can create a custom report (in Administration > Edit Reports) and add a custom section. In that custom section add a query against the R_ProjectReleaseResources entity and that will let you report on resources.
2) You can specify Excel as one of the possible report formats in the Report editing page (Administration > Edit Reports) as well.
Regards
Adam
And if you have any questions, please email or call us at +1 (202) 558-6885