Hi,

In our project we are working with releases and sprints. Each release consists with some sprints, is there a way to add requirements to a sprint AND a release?
Now our requirements are attached to a sprint, but if I want an overview for a whole release there is no way to do that.

Kind Regards,

Bart
3 Replies
Jim R.Jim R.
re: Bart Van Raemdonck on Wednesday, August 20, 2014
Monday, August 25, 2014
Hi Bert

There is no need, a Sprint (aka Iteration) is a child artifact of a Release. If you assign the requirement to the Sprint / Iteration it is automatically part of the release as well.

If you filter requirements by Release, all the child iterations are included.

Regards

Jim
Bart Van RaemdonckBart Van Raemdonck
re: Jim R. on Monday, August 25, 2014
Tuesday, August 26, 2014
How do you link the sprints with the releases?


Bart Van RaemdonckBart Van Raemdonck
re: Bart Van Raemdonck on Tuesday, August 26, 2014
Wednesday, September 3, 2014
You have to indent the sprints and then they are under a release.
Problem solved by the help desk
Statistics
  • Started: 8/20/2014
  • Last Reply: 9/3/2014
  • Replies: 3
  • Views: 8702
Powered by KronoDesk v1.1.0.15 | © Copyright Inflectra Corporation 2011-2016 | Licensed to Inflectra Corporation.