Actual Duration during overnight pause

Thursday, February 18, 2016
Avatar
Hello,

If the test run has been paused overnight, it displays something like 16 hours spent on it whereas actually there was only 2 hours spent. It seems like the Pause is not stopping the duration watch.

How do we fix this?


Same issue has been raised here in 2012. Is there something I do wrong?


https://www.inflectra.com/Support/Forum/spiratest/issues-questions/376.aspx
1 Replies
Friday, February 19, 2016
Avatar
inflectra.sarahx
re: robinm Thursday, February 18, 2016
Hi Robin

You are right, this is a known issue in SpiraTest. The "solution" we added several years back was to allow the tester to manually edit the test run after execution with a corrected Actual Duration.

We have changed how the execution works in the upcoming v5.0 release that will finally fix it once and for all.

Regards
Sarah

Spira Helps You Deliver Quality Software, Faster and With Lower Risk

And if you have any questions, please email or call us at +1 (202) 558-6885

 

Statistics
  • Started: Thursday, February 18, 2016
  • Last Reply: Friday, February 19, 2016
  • Replies: 1
  • Views: 1569